Energy / Technology guide

Power purchase agreements

The commercial bridge between a power project and a buyer starts with what is delivered, where it is delivered and which risks remain.

01 / Technical foundations

How it works.

A power purchase agreement, or PPA, records the terms under which a buyer purchases electricity from a seller. In a physical arrangement, the transaction includes electricity delivery or transfer of title under the relevant market arrangements. An on-site system can sell electricity to its host, while an off-site arrangement needs an appropriate route through the market and network. The useful questions are specific: which project, which delivery point, which period, which volumes and which obligations when actual output differs from the plan?

A financial or virtual PPA has a different structure. It settles a difference between an agreed price and a specified market price, rather than delivering electricity to the buyer's premises. The buyer still needs its normal electricity supply. Renewable energy certificates or other applicable environmental attributes are a further part of the arrangement: their transfer and retirement determine who can make the corresponding renewable-electricity claims. Electricity, price settlement and environmental attributes should therefore be described separately, even when negotiated within the same commercial discussion.

A solar array on flat western Canadian prairie farmland with low foothills in the distance.
02 / Commercial context

Where it creates a useful connection.

A producer may seek a long-term customer to support development or a route to market for an operating asset. A buyer may seek supply, a more predictable commercial arrangement or specified environmental attributes. Those aims are not automatically aligned. A contract based on the project's actual output differs from one requiring a scheduled delivery profile. In both cases, the parties should understand who addresses the gap between generation and consumption. A simple comparison of headline prices can miss the cost and responsibility of serving the buyer when the project is not producing.

The practical starting point is a shared term-sheet brief rather than an assumed standard deal. It should identify delivery and settlement locations, contract volume, duration, commencement conditions, metering, operating responsibilities and the proposed treatment of interruptions. For renewable electricity, the attribute pathway needs to be explicit and consistent with the intended claim. A financial arrangement also requires attention to the relationship between the settlement market and the buyer's actual electricity costs. Specialist legal, accounting and commercial review is needed for the proposed structure; this guide explains discussion points rather than recommending a contract or financial instrument.

High-voltage transmission towers crossing a snowy landscape at sunset in Quebec
THE COMMERCIAL LENS

Define the product before discussing the price: physical electricity, financial settlement and environmental attributes answer different commercial needs and require different evidence.

The system, at a glance

Align the power profile with the commercial need.

  1. 01Generation profileWhen output occurs
  2. 02Delivery structurePhysical or contractual
  3. 03Buyer demandWhen power is needed
  4. 04SettlementPrice and imbalance

A conceptual operating model. Project design and commercial terms depend on the application.

03 / Before the next discussion

Ask the questions
that change the decision.

Use these as a starting point for project-specific technical and commercial due diligence.

Two professionals reviewing logistics plans in a daylight industrial site office
  1. 01

    Does the proposed arrangement deliver electricity, settle a price difference, transfer environmental attributes, or combine these, and which entity performs each obligation?

  2. 02

    Is volume tied to actual generation or a defined schedule, and who is responsible for shortfalls, surplus electricity and changes in consumption?

  3. 03

    What project milestones must be met before supply starts, and what evidence supports the proposed operating date, connection status and delivery route?

  4. 04

    Where are price and delivery measured, who receives and retires the attributes, and which assumptions need specialist review before terms are agreed?

04 / Reality check

What determines
the practical fit.

Modern electrical substation with transformers, circuit breakers, busbars and steel gantries
  • A PPA does not itself create a grid connection, provide backup power or ensure that production coincides with the buyer's consumption.
  • Financial settlements can diverge from a buyer's retail electricity costs when locations, timing or price drivers differ; predictability is not automatic.
  • Renewable-electricity claims depend on the relevant attributes and accounting approach. A project name or power contract alone is insufficient evidence.